King Street Apartments – Week 13

The podium has been poured, finished and stripped. Now that vast majority of the concrete work has been completed.

The framers have been hard at work with more main level framing. They’ve also installed the exterior sheathing with integral insulation. Otherwise known as ZIP R-panel.